Budget value is 0 in current budget could not able to do PO

Dear All,

As per the project we need to give budget in 1st level only and through user status it will be carry forward to all the levels, but in project we have given budget in 2nd level and 3rd level WBSE by mistake, when we did return the budget it become value 0 in 2nd and 3rd level wbse, after that we tried to do PO it saying budget exceed coz of the value 0

kindly suggest how to remove the value 0 from this levels

Thanks & Regards,

Chanty

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Dec 20, 2010 at 06:43 AM

    Hi

    Deactivate availablilty control on the project. Use transaction CJBW, this transaction is project specific. Need to allocate budget again to correct WBS and then continue.

    Regards

    Add comment
    10|10000 characters needed characters exceeded

    • Ok in that case use this Note 1145955 - Orders, WBS elements: Deleting budget, resetting status, create a utility program as mentioned in this note, you can delete a budget for a particular WBSE including the line item. Take help of your ABAPer.