HI Guru's,
We're having some problem's in some of our material types.
When we tried to run the background MRP job, it dont suggest any plan order's, yet we we do it manually (MD02) it suggest plan order.
I check the material master (MRP 1 to MRP 4), storage location all are correct and the same with other materials.
Please advise.
Thanks..