Is it possible to change Planning Plant in General Task list

Former Member
0 Kudos

Hello Gurus,

Is it possible to change Planning Plant in General Task list, ie. for eg.

Earlier I have General Task list Group:22, Group Counter:1, with Planning Plant:0001 & now i want to change/update new planning plant 0002 instead of old 0001 in the same task list.

could you plz suggest me, is it possible? & how to do changes?

Thanks in Advance.

Regards,

Amol

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI Amol,

Its not possible to change the Planning plant , You can delete that task list or you can put deletion flag on it, and go for new creation

Riyaj

Answers (3)

Answers (3)

elvin_enc
Explorer

It is possible to change the Planning Plant, firts of all you have to delete all the operations in the task lis and after can change the planning plant... test it.

Elvin Encarncion

SAP PM Consultant WCM

yogesh_zope
Explorer
0 Kudos

Thanks a lot elvin.enc , your suggested workaround is worked perfectly !!

ruiyang
Discoverer
0 Kudos

嗨阿莫尔,

不能修改,只能重新创建,而且你要检查其他的数据是否一致的情况,要对数据进行及时的修改,然后在重新创建任务列表进行更新数据

Former Member
0 Kudos

Hi Amol,

Its not possible once you create a task list with planning plant.