Planned Cost not update after Confirm Activity

Hi experts,

I'm confirming an activity and adding more work to the forecast work, as shown:

Planned Work: 100H

Actual Work: 50H

Forecast Work: 60H

I though the cost of this 10 extra hours of work was going to be added to the planned cost of the project but is not happing. Is this a normal behaviour? It's possible to see this extra cost in a report?

Thanks

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 15, 2010 at 10:56 AM

    Yes this is a normal behaviour as forecast wont update your planned cost.

    By entering a forecast work you anticipate that the work may consume these many efforts, but you plan for 100 Hrs remains the same.

    You can view the forecasted work in CN47N but not as costs.

    Edited by: ravi kumhar on Dec 15, 2010 11:56 AM

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.