We have two issues:

1- during the creation of the PO (ME21N) , it is possible to change the cost center as many times as we want , the system derives the correct funds center. However, when we save and go back to the PO (ME22N), if we change the cost center, the system derives no more the funds center. If we change the funds center manually to match the const center, the system reinitiate this one ( to one with which the PO was created).

2- When we make MIRO, if we change the fund, for the accounting document, the fund is all the time inherited from the PO. so the invoice and the accounting document have different fund

Please help

3 REPLIES 3

Former Member
0 Kudos

Hi.

'However, when we save and go back to the PO (ME22N), if we change the cost center, the system derives no more the funds center'- check FM document.Also trace derivation.

As a rule FMDERIVE may not update Account assignments on screen in logistic document, for this you need to use badi (PR- ME_PROCESS_REQ_CUST,PO- ME_PROCESS_PO_CUST).

"2When we make MIRO, if we change the fund, for the accounting document, the fund is all the time inherited from the PO. so the invoice and the accounting document have different fund"- trace derivation.

0 Kudos

thanks for your response, the trace gives the correct information. the FM document takes into account the fund center that we have in the PO.

the bodi of the PO is Active.

Former Member
0 Kudos

Hi, i mean trace derivation while me22n, is in fmderive it change?

About badi, it has been not just activated,but with logic of update FM account assignments.