MD07 Stock Days' Supply, First Receipt Days' Supply and Second Receipt Days

Hello,

I am viewing MD07, I would like to understand what are the column values in Stock Days' Supply, First Receipt Days' Supply and Second Receipt Days. Can some one explain in easy language, SAP help is bit difficult to understand.

My status is as below

Material--


Stock Days' Supply -First Receipt Days' Supply Second Receipt Days -Plant Stock

10000010---- -(0.5-)


(4.0)
(0.5-)
--


25000

My Settings in IMG activity "Define receipt elements for days' supply calculation" is

1-- 1 X 2 2 2 X 1 --Blank (Safety Stock)

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Dec 13, 2010 at 06:31 AM

    *Stock Days' Supply:*

    • The days' supply displays the number of days that a material will cover if only current plant stock is taken into account.

    • Starting from the current plant stock, the requirements are deducted one after the other along the time axis. This is done until there is a shortage (requirement > stock).

    *The number of workdays between todays date and the date of the requirement that causes the shortage minus one day. *The value after the decimal point is the ratio between the opening stock on the day of the shortage and the requirement on the day of the shortage.

    • IN your case it is already your shortage of 0.5 days of supply.

    First Receipt Days' Supply

    • The receipt days' supply indicates how many days a material will last

    .*The system takes current plant stock and specific, predefined receipts into account when calculating the receipt days' supply

    • You can define two receipt days' supplies.

    • This enables you to instruct the system to take the less binding receipt elements into account for the first receipt days' supply,

    • When we mean the less binding elements based on the business rule it can be defined like Pur req, STO , Planned order can be your First receip days

    • Like you can mention about the planned order, sto

    • In your case have +4 which means based on the 1st day receipt elements in your config you have 4 days of supply stock with you.

    Second Receipt Days' Supply

    • As explained above it is additional days of supply with few other Receipt elements as mentioned in the configuraiton.

    • take only the binding receipt elements (such as production orders and shipping notifications) into account for the second days' supply.

    • This will have a concurent receipt elements.

    • In youse case you have -0.5 which means based on the second days of supply receipt elements of your configuaratoin you are already out of stock for .5 days of supply.

    Also note:

    The receipt days' supply is not calculated, if current plant stock is negative.

    The receipt days' supply is calculated for a negative plant stock, if the next requirement is in the past

    BR

    DSK

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.