Confirm Activity & Forecast

Hi,

I would like to confirm, partially, an activity and introduce the forecast, the sum of which don't have to be always equal to the planned value.

For example: I plan 400 hours of work for an activity. Later, once the activity is released, I want to confirm that 100 hours have been done but it will be necessary 350 hours more to finish the activity (not only 300 as it was thought). If I confirm 100H as actual work the system determines the forecast work in 300 and If change it to 350 the system will change the actual work into 50.

Which should be the correct procedure?

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Dec 10, 2010 at 03:23 PM

    If you input first actual hours and then remaining forecast, it should not overwrite the actual. We do use the similiar function. If you follow the steps mentioned it should not change the actual.

    Regards,

    Mahendra