on 12-10-2010 3:06 PM
Hi,
I would like to confirm, partially, an activity and introduce the forecast, the sum of which don't have to be always equal to the planned value.
For example: I plan 400 hours of work for an activity. Later, once the activity is released, I want to confirm that 100 hours have been done but it will be necessary 350 hours more to finish the activity (not only 300 as it was thought). If I confirm 100H as actual work the system determines the forecast work in 300 and If change it to 350 the system will change the actual work into 50.
Which should be the correct procedure?
Thanks
If you input first actual hours and then remaining forecast, it should not overwrite the actual. We do use the similiar function. If you follow the steps mentioned it should not change the actual.
Regards,
Mahendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Even I have observed this, If you enter degree of process (%) during confirmation, the actual work and remaining work are determined automatically, but if you change any remaining work now, the system recalculates the actual work. But, instead of entering % , enter actual work and remaining work manually, now the system saves the confirmation without changing actual work based on remaining work.
To remove the influence of '% degree of processing', you can make this field hide from confirmation screen. SO in this way, nobody is allowed to change actual or remaining by changing the 'degree of processing'. 'Degree of processing' is then calculated based on acutal and remaining work. 'Degree of processing' anyway will be visible in the reports.
Regards,
Mahendra
It is very unusual that 'actual work' is getting overwrite after you enter 'remaining forecast'. Are you using BAPI or standard transaction to update the actual and remaining forecast. I know about BAPI, that it does overwrite the actual hours when you try to enter remaining forecast.
Also what is the SAP version you are operating with?
Regards,
Mahendra
Hi,
I must apologize all, I haven't change anything and now is working. I believe that the problem is that I was pressing the return key after introducing the actual work and before introducing the remaining work. I must introduce both values and then press return.
Thank you all for your time.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.