on 12-08-2016 7:34 AM
Hi.
I create one PO and assigned 9 cost center for one item. The PO's quantity is 21.
Then I create a GR document for this PO with quantity 4.
When I create IV reference this PO, it's quantity is 3.999. I thought the IV quantity must be
4. What's the problem? Are there any solutions?
Thanks.
PO account assignment
IV
pure mathematics.
each of your 9 distribution lines are calculated individually based on the entered amount, and rounding according to commercial rounding down to 3 decimals.
The decimal dust of the rounded down values is higher than what was rounded up.
If you add all individual lines to a new total then you don't reach the expected quantity.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
you may want to check OSS note 568541 - MIRO: Default values with multiple account assignment
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jurgen,
For this situation, we can only accept it? And we just tell user, this is SAP's standard and limitation.
Is there any opportunity to change this situation?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.