Dear All,
I plan activity for one day 8 hours & assigned person to activity in CMP2 & distribute work for same day & for same hours,
when i assign same person with diffrent activity with diffrent project with in CMP2 system not showing any message with same person is assigned same day with diffrent project.
How same person can work two project with same time,
Kindly share yours experiance.
Regards
Gajjen
Maintain a project team for the particular WBS and then assign the person to the activity that falls under this WBS. I hope this should not allow the user to be assigned to some other project.
Also let us know from where are you choosing the person from. You can also search the forum. There are some threads available on this issue.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
i assignes persons to work center & when i assign person to activity in CMP2 i am getting list of person which i assigned in workcenter,
Yes i allready searched thread regarding workforce planning but not same,
i will test wht you suggest but it should work with my existing person assignment.
Regards
Gajjen
Hi,
I tested with without person assignment in work center, yes you can assign any person to any project if have capacity but when we distribute work in workforce planning by assignment of person with day & time then same person how can assign to other activity ,because his working hours are fixed,if working time is 8.5 hours & person assign for 8 HR to activity then same person should not work to another activity more than 0.5 hrs,system should not allow.
May i know Standard SAP allow it or not?
Regards
Gajjen