RA for WBS element showing RESA Status

Former Member
0 Kudos

Hi PS experts!

I am new to SAP and have a doubt.

I want to know whether Result analysis (KKA2 or KKAJ) can be successfully done for a WBS element having RESA status.

We use WBS elements to book and post Time (as per project requirement). And so, if I book and post Time on a WBS element which already has RESA status, and then try to do RA (KKA2 or KKAJ), will the RA be successful?

Please help.

Thanks,

Vinitha.

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

Yes - RESA only states that RA has been carried out

Only TECO will dictate no more RA to be done

Former Member
0 Kudos

Thanks for that info.

I had this doubt because I was booking and posting Time on a WBS element (with RESA status) and yet, when I do KKA2, it shows no data; i.e. no WIP or COS. Do you know why this could happen? Why is that the WBS element shows no WIP or COS?

Please help.

Vinitha.

Former Member
0 Kudos

Please check the configuration for RA.If you are booking some cost then it will show the results .