on 12-07-2010 10:56 AM
Hi PS experts!
I am new to SAP and have a doubt.
I want to know whether Result analysis (KKA2 or KKAJ) can be successfully done for a WBS element having RESA status.
We use WBS elements to book and post Time (as per project requirement). And so, if I book and post Time on a WBS element which already has RESA status, and then try to do RA (KKA2 or KKAJ), will the RA be successful?
Please help.
Thanks,
Vinitha.
Yes - RESA only states that RA has been carried out
Only TECO will dictate no more RA to be done