Hi all,
Can apo map the external processing through operation in routing?
We could CIF PDS but the PDS does not take into account the planned delivery time maintained in info record which is seen in operation details under ext. processing tab in ECC.
The steps for external processing in ECC are as under
Subcontracting Info record is created without reference to material,
This info record is added in the operation details under external processing tab.
production version is maintained and ciffed to APO.
PDS is seen in apo.
but during planning in APO it does not consider the plannd delivery time in info record.
Any step missing or its standard behaviour?
Regards
Hemant