Hi,
I have a resource for which the PLANNED DOWNTIME has been maintained as 12 hrs a day for next few months
On top of it, the FACTORY SHUT DOWN (this has been picked from the fact cal) has been maintained in the CAPACITY PROFILE in APO
Logically speaking I should now see AVILABLE CAPACITY as 12 hrs in the capacity profile in the Resource
But I see sometimes as 12 hrs and some times as 3 hrs in the capacity profile in the Resource
and in the planning book I am seing the available capacity as '0'
Kindly share your interpratation , how do I look into this issue to fix
Thanks,
SS