I have a problem in splitting messages inside BPM.

My requirements are:

1. Receive message (message with apprx. 700.000 records)

2. Split message to smaller messages (1 message should not contain more than 10.000 records. 70 messages should be created)

3. Send these message with a delay, one by one. (after the 1. message is sent the next should be sent 1 minute later until all are processed)

My question is how do I split the messages into 10.000 records without using java or abap mapping.

2. how do I send them synchronously in a loop? How should the structure be???

Thanks.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Dec 07, 2010 at 07:34 AM

    Hi Chris,

    You can use a transformation step wherein you will define a 1...n mapping. In the mapping create a logic(in UDF) to split the message after every 10,000 message --> Collapse message. This logic would be there in the root node.

    Hope this helps.

    Regards,

    Rahul

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Can you give a little more information about the UDF?

      I am not familiar with the collapse logic. Thanks.

  • avatar image
    Former Member
    Dec 07, 2010 at 07:22 AM

    Hi guys,

    Any ideas on this?

    Add comment
    10|10000 characters needed characters exceeded