Changing the project schedule dynamically in SAP PS

Hi PS Gurus,

My PS project has the structure defined with WBS, networks, activities and milestones.

This is a construction project. I have the basic wbs elements like 1. Land Acquisition, 2. Procurement, 3.Construction, 4. Handover.

I have dates for each of each one of these steps and the relationsips defined. If there is a change in the one step the remaining steps dates get affected i.e., if the planned date of step 1. Land acquisition changes then the following steps dates should also change.

If i make changes to the schedule of step1, then is there a way PS will take care of making the appropriote changes to the following steps automatically? Is so..please help me how to achieve this. Really appreciate your help.

Thanx.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Dec 04, 2010 at 02:44 PM

    Set automatic scheduling for the network - every time you saave the schedule will be recalculated

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 06, 2010 at 09:26 AM

    HI

    Flag 'Autom.Schedul' should be the soluation for this requirement. But I am not sure, if the flag of network scheduling parameter or rather the WBS scheduling parameter works for this case.

    To double ensure it, please set the flag of WBS scheduling as well. Call the project using CJ2B, button 'Options...'.

    Kind regards,

    Zhenbo

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 03, 2010 at 10:53 AM

    This is standard feature.

    activities in all your steps (WBS Elements) should be interlinked with each other.

    regards