Multi Sourcing

Former Member
0 Kudos

Hi Experts,

I am using Multi sourcing . Here one part is procured from different suppliers let say 5 suppliers(A, B,C,D,E). here i maiantain Quota arrangements 20,20, 20, 20, 20.if in case one supplier(A) was unable to supply 20 parts. and other supplier (B)having surplus of 20 stock. can we make settings B can supply 40 parts , where A can't supply 20 parts.

Regards,

Madhu

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Madhuri

You have defined Quota Arrangement for a particular product, after taking the Planning Run, system will create equal ( say 20 for Total demand of 100) Distribution Receipt Planned at each Supplier (A,B,C,D,E).

For Deployment, you put Distribution Receipt Confirmed as (A - 0 and B - 40). Now you run Deployment with setting - Real Time Deployment.

In this case, while taking deployment run, system will try to take the stock from A. After realizing that A does not have stock, it will fulfill the demand from Supplier with Surplus stock (eg: B in our case).

Please note that in case other Suppliers also have surplus stock, and there is no Supplier selection criteria (i.e. all conditions are same at all suppliers), system may fulfill deficit demand from any supplier.

Hope this answers your query.

Regards

Ankit