Dear Experts,

there is an SAP standard process in ECC defiend as withdrawal from another plant, when for example creating a planned order in ECC, the dependant demand of the component product is placed on the plant assigned e.g the alternative plant. We are using SCM7.0 and SNP as part of our supply chain solution. Can someone advise how and if it is possible to replicate the standard process of withdrawal from another plant in APO SNP?, what settings are essential etc?

Basics of withdrawal from another plant are as follows:-

- create a special procuremnt key and populate the flag withdrawal from another plant, assign to the material master in ECC.

Cheers

Paul Martens

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Pls check the SAP Notes: 577158 for the Doc.

Thanks,

nandha

Former Member
0 Kudos

Nandha,

thank you for the OSS note reference. Very useful. One more question, from this note it suggests that the functionality of withdrawing from another plant is only designed to work with PPDS, is this correct?

Cheers