Usage value not getting calculated for equipment PRTs in production order

Former Member
0 Kudos

Dear PP Gurus,

I have assigned a PRT equipment to pouring production routing.

I have assigned the followings:

1. control key as "1" in the operation.

2. usage value as 1 ea in standard value in the operation

3. Formula maintained in the operation as ZAPF02= SAP_09 * SAP_16

SAP_09 (Operation quantity) -> general operation value , field name- MGVRG

SAP_16(PRT std value) --> Value from PRT allocation , field name- EWVGW

The production order is calculating the planned consumption of PRT usage, but when I confirm the operation, it is not calculating the actual usage usage value. Actual usage value should be number of moulds confirmed in the molding operation confirmation.

Kindly help me urgently.

Regards

Amar

Accepted Solutions (1)

Accepted Solutions (1)

former_member196530
Active Contributor
0 Kudos

Dear

Can you please check whether you any equipment master ?? Did you assign bello points in Equipment Master PRT view

1.Mark Load Record

2.Keep Task List Usage :- 009

3.Usage value formula :- ZAPF02

4.Measuring Point

5.Lastly , in PP Routing add PRT Usage Value

Refer this useful therad from our expert :

Regards

JH

Former Member
0 Kudos

Dear JH,

Thanks a lot for your reply.

I have done the setting which you have directly or indirectly referred.

But still actual usage value not being calculated.

I am concerned about my formula regarding usage calculation.

What are the parameters to be included in the formula.

Regards

Amar

Former Member
0 Kudos

Kindly tell me formula so that usage are calculated on the basis of yield quantity in "MLD" UoM and std usage value 1 MLD.

Former Member
0 Kudos

Actually I don't want to refer std values for the operation. It is confirmation quantity.

former_member196530
Active Contributor
0 Kudos

Dear ,

Regarding PRT usage formula you need to refer the standrad : SAPF02 formula ( SAP_13 * SAP_03 * SAP_09 / SAP_08 / SAP_11)

Just re-cheked what are the parameters really need in your case to frame out the below customised formula as mentioned in your posting : ZAPF02= SAP_09 * SAP_16

Bsically , this usage value is only applicable to equipment PRT .You have to create the equipment as PRT Equipment category. In PRT data you have to assign the (counter) measuring point and maintain the usage formula. Assign the Equipment PRT in the production orders and Enter the usage value and UOM. Ensure the UOM of the usage value and the UOM of the characterestic value you have assigned in the measuring point are same.

Refer SAP Help : http://help.sap.com/saphelp_46c/helpdata/en/fe/67f9609d6f11d189b60000e829fbbd/frameset.htm

Regards

JH

Former Member
0 Kudos

Dear JH,

You seem to be informed regarding the PRT application.

Actually, I have assigned measuring counter in the equipment itself with a char Z_COUNTER_X with UoM as MLD.

Operation unit is also in MLD and std PRT usage value also MLD.

Formula used by me -ZAPF02= SAP_09 * SAP_16 (seems to be correct)

And PRT has been created with IE01 as PRT equipment.

If you can provide me your email ID, I can send you screen shots. I tested this in IDES, but the client got refreshed and I not getting the result again.

Regards

Amar

Former Member
0 Kudos

Hi,

I got the issue.

In IE02- equipment measuring point change, we need to assign the same in the PRT screen also.

But now a new error coming-

Document 3 already entered for the measurement time specified

Message no. IR027

Diagnosis

You are trying to enter a measurement document for a measuring point that has been defined as a counter.

However, a measurement document that has not been reversed already exists at the measurement time you have entered.

The system must be able to determine a unique sequence for the measurement documents to be able to recalculate the counter readings if necessary.

System Response

The system will not allow the existence of two measurement documents for a measuring point where the measurement times are the same to the exact second. The system must be able to order the measurement documents in a sequence if it has to to recalculate the counter readings.

Procedure

Check your entry.

Former Member
0 Kudos

Hi, this discussion is very interesting to me.

Are you be able to solve your problems?

I want to give my experience:

I created PRT, using IE02

I created measurement point as counter and I assigned it to PRT in IE02

I assigned PRT in routing, giving also the formula and the usage value

I created a measurement document

I created a production order

Confirming the order, counter increase, but usage value in production order still remain zero...

Answers (0)