REM planned order conversion to PR with procurement type X

I see that the REM planned order is non-convertible. So, In case of procurement type X where system creates a only REM Planned order (PE order type), we need to manually make the "Convertible" tick mark in planned order and then convert it to PR.

Need to confirm if this is the only way to handle this in REM?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Dec 08, 2016 at 05:56 PM

    Yes, this is the only way. You can try to implement a BAdI to automatically check this field on planned orders:

    https://blogs.sap.com/2013/08/12/badis-for-mrp/

    Regards,

    Caetano