I can create a regular purchase requisition to purchase materials that comes with a delivery ticket through work order system (IW32). In rare cases, where the vendor doesn't provide delivery ticket, receipt or service ticket, I need a service requisition (D).

I can issue a service requisition using ME 51 TC but unable to do so using the work order system.

Please advise if it is possible to order through W.O. system.

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Dec 08, 2016 at 06:17 AM

    Service Requisition (D) comes through Control key PM03 in operations tab of the order. Against this PM03 operations, provide the service details which will be procured so that PR will be generated.