Sched Line On Sales Order Not Updated with Network Date

My client is using Assembly to Order (ETO) where the sales order creates the network and project. The client wants all project date changes reflected on the sales order since many prior custom programs have been developed to read sales order dates. When the delivery date (network finish date) is moved out on the network (especially once any network activities are released) from the original requested delivery date on the sales order the scheduled line item is always updated correctly and the sales order dates match those on the project. However, if the date is moved to any earlier date, the sales order scheduled date remains unchanged. We are not using availability control since this is Engineer to Order. Is there any configuration we are missing which is causing the sales order dates to not move inward but only outward to match the network?

Thanks for any direction you can provide.

JB

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Nov 23, 2010 at 03:15 PM

    There is no standard configuration, that can cause this issue.

    Please check with your ABAP consultant. He might need to change/ update the custom program that has been developed. With you description, I feel that, custom program is only reading the dates that are postponed & it's ignoring preponement of dates.

    Regards,

    Amaresh Makal

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 31, 2011 at 01:33 PM

    It turns out that there was in fact a user exit in SD that the customer had forgotten about from a prior implementation (originally for PP and not PS orders). Once we debugged we found it we proved the user exit caused the problem. The date changes between the sales order and project do flow as expected.