1. Is it possible to do cost estimation at WBS Element in case of ETO?
2. What are the configuration Steps to perform cost Estimation at WBS Element?
3. On what basis we configure Result analysis in case of ETO ?
Appreciation early reply,
Thanks,
Sneha
Hi,
Check the following link which will talk about your requirement...
http://help.sap.com/saphelp_46c/helpdata/en/c7/9d466f0e18d311ae620060b03c9bbe/content.htm
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can also do costing at WBS element level using Easy Cost Planning.
Below link helps on the process:
http://help.sap.com/saphelp_46c/helpdata/en/9d/8e88387f599020e10000009b38f8cf/content.htm
Kind Regards
Umapathi G
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For ETO you would normally develop a cost estimate for the network. Networks are assigned to WBS elements or project headers. You assign a costing variant to the network type and plant combination in t-code (OPUV). You can configure the costing variant in t-code (OPL1).
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.