Hi All,
I am trying to understand block planning with VC; this is what I could understand
· Material (x) will have variant class (300) attached to it. (APO class 400)
· Sales order for material (x) with characteristics values will be entered in ECC.
· Certain % or complete capacity of resource will be modeled using Block Basis Definition in APO using 300 class CIFed to APO
· This class will be assigned to Block Planning view of the resource.
Result
· Based on these characteristics certain portion of the capacity will be pre-booked (reserved capacity). Other orders / products using the same resource will not be able to access this capacity.
· Only specific orders having the characteristics used in block basis definition will be able to use the capacity.
- Please confirm if my understanding is correct.
Regards
Amlan C