Hi experts,

My scenario is:

see 3 site:

- X: Vendor

- Y: Company

- Z: Customer

Please tell me how can i track the cylinder when:

1. Y receipt Cylinder from X (currently I'm using RTP-returnable transport packaging in MM)

2. Y send Cylinder to Z (tracking, Currently I'm using Returnable packaging in SD)

3. when Z dont return Cylinder, Y bill Z, but how X invoice Y?

4. I dont know what is link between Returnable Transport packaging in MM and Returnable packaging in SD. there is 2 special stock.

5. How Y is deposited by X and Y deposit Z?

Y is a agent.

Please help me, how Y tracking Cylinder from X and Y.

THanks in adv

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

I dont have a answer, but I must mark it answered to ask other question.^^

Former Member
0 Kudos

hi ,

When Z donot return the material , it means that you cannot return it to X . Hence inform X about the same so that X raises a debit note on your company (Y ) which can be paid through Payables because he is a vendor for you. Or otherwise Issue a credit note to X ( vendor ) from the business.

When you issue credit note to your Vendor citing the reason for lost of material.

Former Member
0 Kudos

Hi,

Can you tell me which suite Best practise in SAP to solve my scenario?

which is the best solution?

Many thank!

reazuddin_md
Active Contributor
0 Kudos

Hi,

There is no link between Returnable packaging in SD & MM. Both are different process, not interlinked.

You have to map as two processes & develop a report for the tracking purpose.

Either you can use the serial numbers as identifcation key between Cylinders @ Customer site or Company. Some manual interventioin is required if Customer doesnt return cylinder to the company & same has to be informed to the respective vendor or issue a Credit note to the vendor.

Regards,

Reazuddin MD

Former Member
0 Kudos

Hi expert,

This is no link here, but can you give me a solution for this scenario (Y)?

Please.

what do you think about Empty management?

Im a newbie, so I dont know which is the best solution for my client.

Help me,

Thanks

reazuddin_md
Active Contributor
0 Kudos

Hi Kevin,

Not much familiar with Emply Management ( TRM - Task & Resource Management).

Let me try with Concerned who has experience & update you.

Regards,

Reazuddin MD