Hello PP Experts,
I am facing issue with network , prod order and stockrequirement list.
I have a network with qty 2.
1 qty is in stock. (MMBE)
for 1 qty prod order is created and the status is "REL PRT CNF DLV PRC GMPS MANC SECT".
The problem is____________________
Prd order has open requirement and prd ord is still open. The problem is that seem that MRP doesn't take in consideration this requirement as an open requirement and in MD04 it can not be seen. the requirements which we can see have no linked to this production order but only linked to planned orders.
Network can be seen in MD04.
Why prd ord is not visible in MD04.
Mukesh Chauhan