on 11-19-2010 12:02 PM
Hi experts,
Can you please advise on this..
My client has centralized planning.
Ex : 3 maint plant A,B, C.
C is the planning plant for A & B.
Configured order types and assigned the planning plant C (IMG: Assign Order Types to Maintenance Plants).when I do like that Iu2019m not able to see the order types in Define Change Docs, Collective Purc. Req. Indicator, Operation No. Interval .why is it so?
wheter we need to assign maint plants to ordertype and not planning plant?
Regards,
senthil
Hi ,
Just a point to clear , MPP :- Maintenance Planning Plant is the plant where all the Maintenance activities are planned out
MP :- Maintenance Plant is where all maintenance activities are carried out.
So here order is created and planned in MPP and finally the work mentioned in Maintenance Order is executed in MP , from above we need to have all the order type settings to MPP ..,even notification are created in MPP ..
In MP we can have Locations, Eqpts,F.loc ..
hope this is clear ,
regrds
pushpa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.