Hi experts,

Can you please advise on this..

My client has centralized planning.

Ex : 3 maint plant A,B, C.

C is the planning plant for A & B.

Configured order types and assigned the planning plant C (IMG: Assign Order Types to Maintenance Plants).when I do like that Iu2019m not able to see the order types in Define Change Docs, Collective Purc. Req. Indicator, Operation No. Interval .why is it so?

wheter we need to assign maint plants to ordertype and not planning plant?

Regards,

senthil

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi ,

Just a point to clear , MPP :- Maintenance Planning Plant is the plant where all the Maintenance activities are planned out

MP :- Maintenance Plant is where all maintenance activities are carried out.

So here order is created and planned in MPP and finally the work mentioned in Maintenance Order is executed in MP , from above we need to have all the order type settings to MPP ..,even notification are created in MPP ..

In MP we can have Locations, Eqpts,F.loc ..

hope this is clear ,

regrds

pushpa

Former Member
0 Kudos

Thanks pushpa for your prompt response.

So in my case you mean to say all img activity i.e Scheduling, Define Change Docs, Collective Purc. Req. Indicator, Operation No. Interval u2026etc should be defined w.r.t MPP and not MP?.

regards.

senthil

Former Member
0 Kudos

Hi ,

Yes all those settings to be done for MPP ..

Some settings like Define Location in Enterprise Section node and Define Plant Sections are done for MP...

regrds

pushpa

Former Member
0 Kudos

Thanks Pushpa for clarifying my doubt.