I have some activities and they have interdependency. I have scheduled those activities. Due to some reason I havenu2019t started my activity even after latest dates, hence delay in the project. How can I map in the system in such a way that I need reports on schedule over run and cost over run on daily basis.
Regards,
Laxminarsimha
HI
Schedule overrun can be seen as DELAY in the standard info system like CN41N
Regarding Cost Overrun, the requirement should be more clear.
1. If you need cost overrun for the whole project, depending on your availability ctrl settings, you ll get all the standard reports like 87013558.
2. If only the cost over run for those activities in question are to be monitored, how cost overrun occurs when the activity itself is not started?
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.