Typically in SNC Customer Collaboration we have a default source location, that means one single default Transportation Lane.
we need to split the sourcing on 2 different planes like a quotation 25% from Plant A and 75% from Plant B.
This logic is available in APO.
What we would like to develop is a functionality to force the replenishment in SNC before creating planned receipts to read out the valid sourcing via quotations.
So e.g. we have a demand for the ship-to location of 1000, Replenishment should get the information that 250 should be sourced from Plant A and 750 from Plant B.
Based on this planned receipts should be created in SNC Replenishment based on this u2013 also taking into account a rounding.
How to go ahead on this?
Thx