Classic Scenario change Material Group on PR

In a classic scenario can the material group be changed on PR created from approved SC.

We are unable to change it in our enviornment. Please confirm if it is standard SAP behaviour .

Thanks.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Nov 17, 2010 at 05:34 AM

    Hi Kumar,

    You can definitely change the PR in ECC system if you are in Classic scenario.

    Yes, even the material group can be changed in PR.

    In classic scenario the Follow on documents of shopping cart either PR or P.O depending on the setting in the configuration can be changed in ECC system as they are the leading documents.

    Check in case some exits or field controls have been put in place in your ECC system which would disable the ability to change some of the fields in PR.

    Hope this makes you more clear.

    Let us know in case of any further clarifications.

    Regards,

    Teja