Hello Gurus,
I have scinario where Distribution key( equal distribution) in PV which create consumtion type C for output component in PPM.When I convert planne dorder to production order in SCM it is distributing as required and also reflect it in MD04.
However problem is we are using GR processing time which gives a ver diffrent behaviour in SCM v/s ECC.
eg we have production order starting from 11/15 till 12/20 including 10 days GR processing time( order starts 11/15 and complete production on 12/10 and from 12/10 to 12/20 is Gr processing time)
In ECC it shows the order distribution start on 11/25 and completes on 12/20 which is correct. But in SCM the distribution is showing start from 12/10 and ends on 12/20.
Any body know how we can can match ECC and SCM?