multiple PR to single PR through mrp run

Hi all,

Please go through followings.

Lotsize u2013 ex, strategy u2013 40, MRP type - PD.

Indv/col u2013 indicator 2

minimum lotsize -1500,

rounding value 250,

Planned Deliv. Time -7,

GR Processing Time -1,

Processing time -0.

Mrp is run 11/15/2010 (mm/dd/yy)

Receipt/

Rqmnt date ======== Rec/Reqd Qty avail able qty

Stock =============2,447----


1,172 (Safety stock - 1275)

07/23/10=========== 290----


882

07/24/10=========== 10----


872

07/26/10=========== 45----


827

07/27/10=========== 750----


77

11/15/10=========== 20,138----


20,061-

11/18/10=========== 2,750----


22,811-

11/19/10=========== 990- -


23,801-

11/20/10===========312----


24,113-

11/24/10===========735----


24,848-

11/25/10===========513----


25,361-

11/30/2010 -


> End replenishment lead time

=====================PR No ================Reschedule date=========PR quantity==available qty

11/30/2010 PurRqs 0011217291/00010---- 11/15/2010 - 30 -- 20,250-- 5,111-

11/30/2010 PurRqs 0011217292/00010---- 11/18/2010 - 30 -- 2,750 --- 2,361-

11/30/2010 PurRqs 0011217293/00010---- 11/19/2010 - 30 -- 1,500 --- 861-

**I donu2019t want to change lotsize.

Why system proposes 3 PR?

How can we make it single pr through MRP run automatically?

Edited by: nirmalari on Nov 15, 2010 11:01 PM

Edited by: nirmalari on Nov 16, 2010 12:02 AM

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Nov 15, 2010 at 11:06 PM

    Nirmalari,

    The system is proposing 3 PurRqs because you have three different requirements, and you have selected lotsize of EX. The dates are all the same in the PurReqs because you do not allow start dates in the past. EX means lot-for-lot. 3 requirements generally means 3 proposals (Purchase Reqs). I would normally recommend that you change your lotsize policy, but you have already stated that you don't wish to do that.

    Best Regards,

    DB49

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 16, 2010 at 03:04 AM

    are you maintaining any replenishment lead time in material master

    Why system proposes 3 PR?

    reschedule date is different that the reason system created 3 PR

    since the end of replenishment date end on 30 th, system will reschedule the pr based on setting maintained in OPPQ- rescheduling - tolerance value forward

    system will propose the requirement on the requirement date if rescheduling is happening

    on 15 the requirement qty is 20250( reqmt - stock) system proposes rescheduled PR on that date

    0n 18 th requirement is 2750, system create a PR for 18 th

    0n 19 th since you have maintained min lot size as 1500, system proposes 1500 qty on 19 th

    I hope it will clear you doubt

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 28, 2010 at 07:43 PM

    done

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      I have the exact same problem.

      I get three requisition for same material and no idea why.

      My lot size is MB so I dont understand why it doesnt suggest one requisition with the quantity needed for the month?

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.