Hello,

when a user creates an incident with webdynpro-page "ags_incident_trans_key", he can do activities with the buttons "answer", "confirm" and so on. After he triggers one of these actions, an insert in the protocol is written by the Solution Manager automatically. This insert doesn't work, when the action "confirm" is aktivated. The status of the incident-document changes into "quittiert" and I'm not able to do any changes (that's ok). But there is no insert in the log! So it's impossible for me to see, when this incident was closed. The user has CRM_TXT_ID --> ACTVT = 03 and TEXTID = SU15.

When this status is triggerd with button "action", everything is ok. But this is only possible, when CRM_TXT_ID is customized with ACTVT = 02,03 and TEXTID = SU15.

Thanks in advance,

Ralph

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Nov 16, 2010 at 07:33 AM

    hi

    pls chk the SAP note [Note 1497171 - Work Center: Wrong user status set when you confirm messages|https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1497171]

    Thanks,

    Jansi

    Add comment
    10|10000 characters needed characters exceeded

    • Hello Mr Dollinger,

      As far as I know, the actions will be executed in the order set by the sort order of the actions, not the order in which you select them. Also, changing the status by hand is not an action, so I guess that the status change would only be reflected in Extras -> change documents.

      I think there should be a way to include ppf actions triggered by status changes, but the problem is that when doing this with status 'confirmed' or 'withdrawn' then the changes are no longer possible, so I don't see how to add text to a message log when closing it from the status menu.

      Best regards,

      Miguel AriƱ