Rough cut planning & available capacity

18 Views

I need one clarification, in the rough cut planning, the existing load

is not considering for available capacity.It is considering only from

the resource capacity.

E.g : Avaialble capacity of for Resource A (today) is 24 hr

One Order is created and released for 4 hr with Resource A

As per that now my available capacity of the resource is only 20 hr

In SOP planning view, it showing as 24 hrs.

And If i am running the SOP today at 1400hrs for calculating the

resource capacity. Practically my avaialble capacity is 10hrs. But

in the system it showing as 24hrs.

How to capture the above both requirements?

2. Through roughcut planning we can able calcualte the cost, material and

PRT availability also. But it is not coming the the SOP screen.

Is it any configuration i missed out? Help me out

Regards,

sakthivel