Hi PP Gurus,
Can you help me in this problem. In my client's company there are operation and in operation secondary resource is also there. User confirmed 1st operation and then confirming second operation. But I want to make such a setting that user should first confirm all the secondary resource and then 1st operation and then system will allow to go 2nd operation.
Jayesh
User Exits for T-code COR6 can help map your requirement.
Best Regards,
Raghavendra K Nayak