"Closing" Unused, but Released Orders with Inspection Lots

Former Member
0 Kudos

We have Process Orders which have been released, but been unused. When We come to Financially Close them we have problems as the Inspection lot is still on without a UD

Is there a way we can mass process UD of Inspection Lots (or deletion of IL) with Nothing Produced on the Order?

Thanks & Regards,

Vivek Kumar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

if you the process orders, make a list of those. now in qa16, you can do the mass UD. in that transaction, you can find out an option called " dynamic selection". if you expand that option, you will have an option called " production"; under that order. So you can put all those process orders and with the lot oringin 03, you will ge tp know the concerned inspection lots. then you do mass ud. this was your requirement.

Partha

Answers (2)

Answers (2)

sundaresan_velayudam
Active Contributor
0 Kudos

if the process order is unused, then do the re-read the master data in process order , system will delete the inspection lot , if the order is release then only inspection lot will be created

Edited by: Sundaresan . E. V on Nov 11, 2010 9:50 PM

sundaresan_velayudam
Active Contributor
0 Kudos

if the process order is unused, then do the re-read the master data in process order , system will delete the inspection lot and then set the status as TECO