I have one Infopackage which already exits in one main process chain that run once a day. But, now I want to run this infopackage 4 times a day. Does anybody know how to make it possible in this main process chain?

Accepted Solutions (0)

Answers (6)

Answers (6)

Former Member
0 Kudos

Are you using the native process chain scheduling? (Vs using Control-M to call the process chains)

1) I assume you can't remove the InfoPackage from the existing process chain and put it into a second chain that runs every 6 hours.

2) You can create 2 additional process chains. 1 that runs every 12 hours. And one that runs once a day. Then just set up the times so that these are 6 hours apart

Former Member
0 Kudos

Make a separate chain with only the infopackage and schedule it 3 times a day.

And let the main chain containing the infopackage run once a day.

Former Member
0 Kudos

Hi,

You can schedule like this,

Main chain :

Period : Daily

Time :00:00

New Chain

Keep 3 Schedule

Schedule 1:

Period :Daily

Time :06:00

Schedule 2:

Period :Daily

Time :12:00

Schedule 3:

Period :Daily

Time :18:00

former_member102099
Participant
0 Kudos

HI,

create a new chain and include this infopackage only.

schedule your old chain only once and schedule this new chains 4 times in a day the way you want.

you may need to keep the dependency for the previous chain to be succesful .

Regards

Ajeet

Former Member
0 Kudos

in this way that means I will run 5 times of this infopackage a day. That I don't want to do.

former_member209702
Active Participant
0 Kudos

Hi,

In this case scedule new process cahin with infopacakge to run 3 times..

4th time it will run in your main chain.

- Geetanjali

Former Member
0 Kudos

Hi,

If i a have understood correctly, you just want to run the Infopackage (which is in the chain) 4 times a day.

If its only the Infopackage, you may not be able to do it in the same chain, as this would result in the whole chain getting executed 4 times.

You can create a new chain with the Start Variant & the Infopackage in it & schedule it to run as per your requirement.

Hope this helps.

Regards

Vishal.

Former Member
0 Kudos

u want to run the process chain 4 times or just the infopackage 4 times?

Process chain can be scheduled by difference of 6 hours thus 4 times in a day.

Former Member
0 Kudos

I want to run infopackage 4 times a day, but keep running the process chain only once a day. Any advise? Thank you