Dear Sir/Madam,

Is it possible to create reservation for production order at plant level despite of production storage or Raw material storage location. During availability check when it check material availability at plant level, it is not including reservation which is generated against previous order because these reservations are generated previously at production storage location not at plant level. in my scenario we bring the raw material from raw material storage location to production storage location (By 311 movement) after production order release.I want to perform availability check at plant level, keeping all the previous reservation in account. My OPJJ settings and mmbe screen shot are in attachment. Kindly look into this.

Regards,

Dhiraj Dua

Accepted Solutions (0)

Answers (1)

Answers (1)

lingaiahvanam
Active Contributor
0 Kudos

Hi Dhiraj,

Material reservation created based on storage location maintained in the production order components (material master, BOM).

If storage location maintained reservation allocated at storage location level if storage location not maintained reservation consider at the plant level.

mmbe.png

mb23.png

Best Regards,

Lingaiah