on 12-07-2016 11:04 AM
HI All,
While creating PO user do not know delivery plant. They create PO in bulk(send it to vendor) and then tell vendor to dispatch materials to other plants as per requirement of material.
User is saying they do not want to enter plant in me21n as they do not know. Plant is mandatory field in PO creation.
How to handle this in SAP?
there is no straight way in SAP. Whatever workaround you do you add a lot of extra work.
Workaround could be to create this order outside SAP and maintain it only in SAP once everything is known - you then have no information within SAP to know what is needed, already ordered and when it is supposed to come.
You can create a contract without plant and can later create call offs(POs) against this contract, which is double work in SAP.
A process usually starts with a requirement and this requirement is a certain site (plant).
What is the business scenario that the plant is not known at this time?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
I would sugegst to create a contract for the bulk quantity and then create release orders with required quantity and plant whenever required.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.