ECP vs CJ20N planning

Hello gurus,

I have activated the Planning for Network Activities with Easy Cost Planning.

My doubt is which is the common procedure to plan with ECP.

If I plan the ECP, do I need entry the hours in Work field into the network activity too? I tested that if I do not entry the Work hours I cannot do the person assignment, but if I plan both (ECP and CJ20N) I am duplicating the planning, unless I change the versions, for example ECP version 1.

But if the solution is this last one, I need to entry twice the same planning, one in CJ20N (Work) and another in ECP. How can avoid this double entry to planning?

I hope my doubt has been clear.

Thanks for your help.

Anibal

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Nov 09, 2010 at 05:21 AM

    then use network costing alone, Why do you want to plan both on ECP and Network costing?

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 13, 2010 at 01:06 PM

    my total planning/actual cost is not getting updated when i go to costs from activities/network (edit->costs->activies/network) if i do not update the date.

    What exit should i use for it or what is the way to solve it?

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Please check the settings costing variant plan, costing variant actual & plan cost calculation in Network type parameters (SPRO)