Hi,
This is a question for IM experts ( I am not sure If it is the correct forum),
We need an appropriatrion request change its status to replaced by measure, but measure ( WBS) is not going to be created from the measure even if from CJ20 transaction and then is associated to the AR.
Is this possible?
Thanks,
Sara
If you are not goint to create or assign measure to Appropriation request then I dont think it is possible.
Hi all,
This is my actual flow:
Create Appropriation request ( attached to a investment program) --> create a project ( from AR) --> Change status Replaced by measure --> when budget is approved my WBS is linked to program position (IM52).
Now we can draw this flow :
Create Appropriation request ( attached to a investment program) --> create a project ( from CJ20) --> attach project to AR when budget is approved my WBS is linked to program position (IM52).
In this second case WBS doesn't appear in IM52 linked to the porgram and I suppoused that the problem was related to the status of the AR.
Thanks,
Sara
Thanks a lot for your help,
The problem Is we have a WBS assigned to a AR and AR assigned to investment program, when AR is approved we need have WBS assigned to program inversion to share the budget but we have to :
1) delete AR --> WBS assigned
2) assign WBS to PI
to achieve thisis.Budget is approved for several WBS if we make step 1 we lost the relation
AR bears the approval levels, Cash flow statistics, NPV, IRR , Pay Back period calculations
Project is the Executing object of the concept where as AR is the pre project Investment Request which justifies the Investment.
Even though we delete the AR (replace with measure),,, without this Investment decisions cannot be taken.
regards