Incorrect Proc. % of Work aggregated if different unit of work

Hi,

Am having a Root WBS under which I have a network with 2 activities:

Activity 1 -> Forecast Work = 50 HR, Actual Work = 20 HR (partially conf.)

Activity 2-> Forecast Work = 60 MIN, Actual Work = 10 MIN (part. conf)

In CN41N,

Proc. % of work for Activity 1 = 40%

Proc. % of work for Activity 2 = 17%

But WBS gets an aggregated % of 27. I think it is simply adding up actual data and dividing by forecast without considering the unit of work. Ideally it should have converted data into one unit and calculated the correct value as 39.5 ~ 40%.

The Note 1297169 already exists as per my patch level. Anyone facing this issue?any other note that can be referred?

regards

V Guru

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Nov 02, 2010 at 05:55 PM

    Its good that you have found the solution on your own, Why dont you apply the note straight way and see whether your problem got resolved or not? Why do you want another note for this. I dont think several notes will be issued for same problem, so just try the note and see.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi all,

      SAP released a note for this.

      Note 1530484 - CNS41/CN41N: Incorrect "Percent of completion for work"

      Warm Regards,

      Guru