Counter Based Maintenance

Former Member
0 Kudos

Hello All

Can any one let me know how the counter based planning can be execute.

If the maintenance is required oon one equipment after 300 hrs & 1000 hrs.

I try to do this but not able to execute properly

1) create equipment

2) create 2 measuring point against the same equipment.

3) create cycle (ip11z) with same frequency.

4) create plan (ip43) and then assign the cycle set and then attach both counter to that plan.

5) after scheduling ip10 then creating measuring document

6) finally move to dead line monitoring

here at 260 hour the system is generating order but that order contain operation of both frequency (300 hrs &1000 hrs)

i also check the hierarchy, in (ip11z ) the hierarchy field is not available like as in ( ip11)

Thanks in advance

kapil

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

if your looking for Maintenance every 300hrs and every 1000hrs then you can go for Strategy Cycle Plan in IP42 ..

You can maintain one measuring point only and enter enough measurement documents , you can create strategy first in IP11 and mention all package cycles are 300 , 1000 & hirerachy details ...you can use offset to have some changes in the cycles within the plan .. you can use this strategy in IP42 and schdule in IP10 and test up ..

regrds

pushpa

Former Member
0 Kudos

Hello Pushpa

Initially thnx for giving your precious time ,, as you has suggested i had already tried the same many time but the problem in strategy based planning is in ( ip42 ) there is no field to attached the counter like in ip41 & ip43.

With out counter how the system will came to know that how much hour actually runs and need to generate the call object.

if there is any altrenate sugestion then pl let me know the same

Regards

Kapil

Former Member
0 Kudos

Hi,

it looks like you are using time base strategy.

Change it to Hour based staategy then you will get Counter in maint. Plan Screen.

regards,

Sandeep

Former Member
0 Kudos

Hello Sandeep

Thnx for your reply but still i am in vain pl have a look elow what i did

I create strategy (E)

Scheduling indicator u2013 time

Strategy unit- H also mention call horizon, n some other parameters

In Packages

1) 288 H 300 hour 1H 1

2) 984 H 1000 hour 2H 2

hour UOM Description Short Descript Hierarchy

Then I create M-Plan via IP42 with the same strategy and attached the task-list. So there is no field to put the counter

May be I am wrong some where ,just review the same and let me know if miss some thing

Regards

Kapil

Former Member
0 Kudos

Hi,

"I create strategy (E)

Scheduling indicator u2013 time"

Scheduling indiacator should be acitivity .

i hope this will resolve your problem.

Regards,

Sandeep

Former Member
0 Kudos

Thnx Sandeep

my issue has been resolved now its working fine