Rem order plan value exist for difference between PO & GR value

Dear Experts ,

In PS report S_ALR_87013558 it is found that the difference between Service PO & GR value is reflecting in Rem. Order plan.

against the WBS.

According to my understanding the difference between Material PO value & GR value reflects as outstanding commitment. Hence I assume that the same should happen in case of Service procurement also.

Kindly let me know whether the reporting is correct or not.

If the reporting is incorrect, then what could be the reason for the same and how this problem can be tackled.

Regards,

Vishal

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Oct 30, 2010 at 07:39 AM

    No, ROP is no claculated in that way....try reconstructing your database and also check other reports.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 30, 2010 at 02:56 PM

    Hi

    Check if you have ticked remaining order plan value updation under costing in customization (both check boxes). If those are checked your plan value becomes assigned values always and if there is any residue it will be there under plan value.

    Also note that for service PO, once all entry sheets are posted, for final entry sheet user should click FINAL ENTRY in SES. It will remove any residual commitment.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.