Possible to link prod version of top level mat with prod vers of component?

Material A has a BOM that has 2 production versions, Version 1 and Version 2 (2 different production lines).

The BOM contains semi-finished material B. B also 2 production, Version 11 and Version 12 (2 different production lines also).

When for planning/costing Version 1 is used, it should always pull in Version 11 of the component BOM.

If Version 2 is used, it should always pull in Version 12 of the component BOM.

Any idea how we can control this? I canu2019t see where to link in the lower level production version.

Thanks a million

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Posted on Oct 28, 2010 at 09:00 AM

    Dear Oil,

    If my understanding is correct while doing costing run in CK40N, for the finished product level,the system automatically first costs

    the semi-finished product level and then at the finished product level.

    The system pick the relevant BOM and routing for the sub-assemblies and after costing this,this value is used as the cost for the

    higher level material.So in this case the system first picks up the first production version by default and the BOM and routing

    which is linked gets picked up.

    In case if this does not works,assign the production versions that's to be considered for costing,assign this in the costing 1 view

    of the material master and check the impabt during cost rollup using CK40N.

    Correct me if I'm wrong.

    Regards

    S Mangalraj

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 28, 2010 at 08:55 AM

    Dear OII,

    Via CK11N there are two ways to perform costing

    One way is material level and second way is PV level

    Check the third Tab of CK11N you can get option production version

    Regards

    Madhu

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 28, 2010 at 09:00 AM

    Dear Oil,

    If my understanding is correct while doing costing run in CK40N, for the finished product level,the system automatically first costs

    the semi-finished product level and then at the finished product level.

    The system pick the relevant BOM and routing for the sub-assemblies and after costing this,this value is used as the cost for the

    higher level material.So in this case the system first picks up the first production version by default and the BOM and routing

    which is linked gets picked up.

    In case if this does not works,assign the production versions that's to be considered for costing,assign this in the costing 1 view

    of the material master and check the impabt during cost rollup using CK40N.

    Correct me if I'm wrong.

    Regards

    S Mangalraj

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.