SAP Scheduling Plan Vs Actual

While doing Scheduling through SAP using internal activity dates get change on every scheduling . Requirement is of Plan vs actual schedule.

Is there any method apart entering plan dates in user field.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Posted on Oct 28, 2010 at 04:11 AM

    There are two options:-

    1. Make use of project version, to compare the dates of past and present.

    2. copy the basic dates to forecast, and compate the present basic date with forecast. do not schedule forecast dates, so that it remains unchanged.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 28, 2010 at 05:48 AM

    Thanks first option will work but option second i.e will be valid for WBS but i have many internal activities for single WBS and comparision is required for various activities.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.