on 10-27-2010 10:47 AM
Hi,
Can anybody please explain me following entries in table PBHI?
CL. Req Pointer Finish Dt Last Change Time Planned Qty Withdrawl Qty Plnd qty in database
400 109865 02.10.2010 14.09.2010 16:57:55 3,100.00 0.000 0.000
400 109865 02.10.2010 27.09.2010 17:04:13 4,000.000 2,000.000 1,100
400 109865 02.10.2010 03.10.2010 11:41:03 4,000.000 2,500.000 3,500
Regards,
Samir Wadajkar
It traces the history in the demand management, you have the
Client
requirement number ( link to table PBIM to know the material code)
Dates
Original plan
Withdrawal quantity (goods issue linked to this planned quantity)
qty in database (historical value )
Link this table with PBIM and you will have a complete picture. link thru BDZEI field.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.