Hi experts,

I have an issue based on the screen control of master recipe..... When i create a master recipe with control key which is defined for external processing 10 mandatory field have to be entered under external processing data......Now i want only one field to be mandatory...So how can i make the necessary screen control..????

Regards,

Joseph.

Edited by: joseph5885 on Oct 27, 2010 11:07 AM

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

I am not sure please try to set it correspondingly adjusted the customizing settings of the plans for the field grouping (Path: Production -> Basic Data -> Routing -> Control Data -> Define Field Selection). (Transactions OP5D and OP5A)

access the operation view via the transaction of the recipe maintenance (Task list 2), Please try and come back.

If you want to process an operation externally, you must create at least one phase for this operation and then have it processed externally

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi Brahmankar,

Thanks a lot for ur reply.....

I checked in OP5D and all the fields are selected optional ie. input...No field is selected as mandatory...But while creating master recipe the values in external processing data is mandatory.....Can u tell where else we can give the mandatory options for control key....???

Regards,

Joseph.

former_member196530
Active Contributor
0 Kudos

Dear ,

You can assing this in Resource -CRC2-Default Values -Control key and it will flow automatically in Master Recipe .

But if you are looking at master recipe level then put a screen variant SHD0 for C201 where Operation control key can be mandatory filed

Refer : http://wiki.sdn.sap.com/wiki/display/Snippets/TransactionVariant-AStepbyStepGuidefor+Creation

Try and chek

Regards

JH

Edited by: Jiaul Haque on Oct 27, 2010 8:48 AM

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

For external processing operation SAP has given some filed as mandatory like Purchase Info Record, tick mark for Sub-contracting if you use the control key as PI02. You can not change this setting.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi Jiaul,

Thanks for your reply.....

Rite now when an operation is given a control key having external processing indicator its going to the mandatory field in external processing in general data tab...There is no screen variant defined for this T code C201 and no field selection in OP5D as mandatory....but also system pick mandatory fields in master recipe, general data ....Where can we customize mandatory fields for control key....???

Regards,

joseph

Answers (0)