BADI or EXIT while Checking Budget of PO against WBS

Hi ,

while creating the PO there is one pop us is coming. In tha pop up warnings/errors are coming.

There is one warning which is stating: Budget is almost exhausted.

Now I have one requirement that while checking budget by summing all condition type value, I need to exclude on condition type.

Means when the pop is coming for thes warning, before that when it is comparing the values, we need that particular condition type value should not be considered.

Kindly help where to write code for this and if any BADI or EXIT exists

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Posted on Oct 26, 2010 at 11:34 AM

    I'm not sure this kind of exit/badi may exist, budget is checked in CO controlling, not in MM, so the commitment value is transfered to CO, and i don't think you can change this value ?

    Regards,

    Raymond

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.