Transfer Posting Material to SubContractor

Former Member
0 Kudos

Dear Experts,

Can we Issue material which are not included in the Subcontracting PO Item BOM to a Sub Contractor.

Regards,

Suman.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Yes, you can maintain manually those parts which are not in the BOM at the time of MB1B.

If you entered parts with the +ve qty, system will post with 543 movement type.

If you entered parts with the -ve qty, system will post with 545 movement type.

Regards

KRK

raviraj_sharma
Active Contributor
0 Kudos

yes you can , through MB1B without referring the PO.

But why exactly would u want to do that? It will not get consumed when u receive the finished material, you will have to take it back by 542 manually.

Former Member
0 Kudos

Can't we make Subsequent Adjustment.

Regards,

Suman