Can we Issue material which are not included in the Subcontracting PO Item BOM to a Sub Contractor.

Regards,

Suman.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Oct 25, 2010 at 02:21 PM

    yes you can , through MB1B without referring the PO.

    But why exactly would u want to do that? It will not get consumed when u receive the finished material, you will have to take it back by 542 manually.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 25, 2010 at 02:32 PM

    Hi,

    Yes, you can maintain manually those parts which are not in the BOM at the time of MB1B.

    If you entered parts with the +ve qty, system will post with 543 movement type.

    If you entered parts with the -ve qty, system will post with 545 movement type.

    Regards

    KRK

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.