Skip to Content
0
Former Member
Oct 25, 2010 at 12:01 PM

WBS dates not update in report

41 Views

Dear All

I have created Project through Sales Order. Delivery date in sales order is end date of project

All activities are link (established relationship) one network and assigned to WBSEs in project.

I have also mentioned the normal duration for each activity in network.

I am doing scheduling of these activities with following specific requirements -

1) Backward scheduling is to be done...start date for network can be either today's date or it can also be in the past...end date for completion of network is fix.

2) Scheduling is to be done on entire project, the dates should be determined by the system for activities and should be transfered to the respective WBS elements (i.e. network determined dates)

I have maintained following config settings -

Scheduling Parameters -

Adjust date - 2 (do not adjust)

Scheduling type - 2 (Backward)

Automatic scheduling - Ticked

Reduction strategies - All opern in the order

Parameters of Scheduling -

Backward, network det date, adjust basic dates (tick), Automatic scheduling (Tick)

when I run scheduling for entire project its gives result properly but in report CNS41 my dates for ErlStrt(B) F and LtStrt (B) for WBS seen ##.##.#### .

Do I need to change anything in the config???

Regards