cancel
Showing results for 
Search instead for 
Did you mean: 

WBS dates not update in report

Former Member
0 Kudos

Dear All

I have created Project through Sales Order. Delivery date in sales order is end date of project

All activities are link (established relationship) one network and assigned to WBSEs in project.

I have also mentioned the normal duration for each activity in network.

I am doing scheduling of these activities with following specific requirements -

1) Backward scheduling is to be done...start date for network can be either today's date or it can also be in the past...end date for completion of network is fix.

2) Scheduling is to be done on entire project, the dates should be determined by the system for activities and should be transfered to the respective WBS elements (i.e. network determined dates)

I have maintained following config settings -

Scheduling Parameters -

Adjust date - 2 (do not adjust)

Scheduling type - 2 (Backward)

Automatic scheduling - Ticked

Reduction strategies - All opern in the order

Parameters of Scheduling -

Backward, network det date, adjust basic dates (tick), Automatic scheduling (Tick)

when I run scheduling for entire project its gives result properly but in report CNS41 my dates for ErlStrt(B) F and LtStrt (B) for WBS seen ##.##.#### .

Do I need to change anything in the config???

Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member203108
Active Contributor
0 Kudos

Try with CN41 / CN41N and then check the dates.

Former Member
0 Kudos

Hi Ahemad

The issue was same with all reports. The date was display properly in WBS under dates tab or even I able to view report from CJ20N through Project Planning board (gantt chart) by selection of dates field. I only get problem under to column ie ErlStrt(B) and LtStrt (B) where dates was reflected ##.##.#### only for WBS but activities under same WBS dates shown properly.

Regards

raghavendra_praveen
Active Contributor
0 Kudos

Hi

Did you check the dates in project planning board? I believe the field lenght is not suitable to display in your case (generally ##.##.#### means improper display). Also try to check scheduled dates after scheduling (hope you used shift dates after any improper scheduling results..if not try once).

Former Member
0 Kudos

Hi Praveen

Field Length I have maintain as per length required, there is no issue related length. In Project Planning board dates are display appropriately. The duration of project not more than 100 days and I try the option of shift dates with rescheduling but still not get result

Regards

former_member203108
Active Contributor
0 Kudos

Check this Note 1102600 - Fields without a date are displayed as ######### , apply this, it may solve your problem.