Date of BOM Explosion/Routing in the production order

Dear gurus,

i would like have the Date of BOM Explosion/Routing in the production order same the "Basic start date" .

I setting the value 1 = Basic start DATE in the customizing transaction OPPQ and OPPR but the system calculate this date wrong.

Are the the other setting for this necessity ?

Thanks a lot

Daniele

PP TEAM

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Oct 25, 2010 at 10:40 AM

    hi,

    Check the scheduling strategy whether forward or backward scheduling you have used.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear gurus,

      i used the backwards scheduling strategy , but i need explode the bom whit the "start basic date".

      The explosion date is calcolate only from type scheduling ? The flag in the transaciont (OPPR , OPPQ ) don't are actived or use from system ?

      Thanks

      Daniele Pistilli

      PP TEAM

  • Posted on Oct 25, 2010 at 11:16 AM

    Dear Toto,

    The standard procedure is that the system first checks whether a BOM explosion number exists for the BOM. If one does exist,

    the BOM is exploded using the fixed key date contained in the BOM explosion number. If a BOM explosion number does not exist,

    the BOM is exploded with the order start date.

    Check the setting in OPPQ for BOM explosion.

    Regards

    S Mangalraj

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 25, 2010 at 11:17 AM

    Dear Toto,

    The standard procedure is that the system first checks whether a BOM explosion number exists for the BOM. If one does exist,

    the BOM is exploded using the fixed key date contained in the BOM explosion number. If a BOM explosion number does not exist,

    the BOM is exploded with the order start date.

    Check the setting in OPPQ for BOM explosion.

    Regards

    S Mangalraj

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 25, 2010 at 11:23 AM

    Dear

    Did you keep the BOM Explosion in as Order Start Date (1) OR BOM Explosioin number /Order Start Date -3 in OPPQ ??

    Same has be maintaind if you are following MRP group in OPPR .

    Check this two set up and come back

    Regards

    JH

    Edited by: Jiaul Haque on Oct 25, 2010 1:23 PM

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.